Question 14 • EA Academy Online Learning and Digital Citizenship Elective Spring
A project schedule is a plan, and actual work may take more or less time than expected. Members should review progress and make periodic adjustments when needed so the project can stay on track. Making changes only after someone falls behind may be too late, while dropping other activities or completing a survey is not a general scheduling responsibility.