Inequalities — Unit test

Question 16 of 25 • FL-1200700-Mathematics for College Algebra MIS

Paul can install a 300-square-foot hardwood floor in 18 hours. Matt can install the same floor in 22 hours. How long would it take Paul and Matt to install the floor working together?

Answer
A
4 hours
B
9.9 hours
C
13.2 hours
D
30 hours